Project Details

We offer smart, reliable EV charging solutions built for every need. From installation to management, -seamless and efficient.

Harbourside Business Park

Harbourside Estates manages 18 tenants across five buildings, and nearly a third of employees were already driving electric. Demand for charging was outpacing the park’s single standby supply.

Evolta surveyed the site, modelled demand for the next decade and designed a combined AC and DC installation that shares one new 800 kVA connection through dynamic load balancing. Staff bays are access-controlled; the visitor forecourt accepts contactless payment.

Location

Bristol, UK

Sector

Workplace charging

Capacity

1.1 MW

Duration

14 weeks

Completed

June 2026

What Went Into The Ground.

The site received a new 800 kVA connection, 1.4 km of ducting and cabling, and a load management controller that shares power between 28 chargers in real time.

The programme ran in three overnight phases, so every tenant kept full car park access throughout.

Delivery
0 Wks
Chargers
0
New connection
0 kVA
Overnight phases

From Survey To Switch-On In Four Stages.

A predictable path with a named project lead at every step, so there are no surprises on cost or timeline.

Step 01

Survey & Plan

On-site survey, demand modelling and a fixed-price proposal with layout drawings.

0%

Step 02

Design & Permit

Hardware selection, load management design, DNO applications and consents.

0%

Step 03

Install & Commission

On-site survey, demand modelling and a fixed-price proposal with layout drawings.

0%

Step 04

Operate & Support

On-site survey, demand modelling and a fixed-price proposal with layout drawings.

0%

Specified For Uptime, Ready To Expand.

Equipment was chosen for reliability, open standards and room to grow. Every unit is OCPP compliant, so Harbourside Estates can change software providers later without replacing hardware.

AC chargers

24 × 22 kW Type 2, wall and pedestal mounted

DC chargers

4 × 60 kW CCS2, visitor forecourt

Load management

Dynamic balancing across all 28 units

Payments

Contactless, RFID and app

Monitoring

24/7 remote diagnostics and usage reports

“Evolta handled everything from the grid application to commissioning. The monthly usage reports make the business case obvious to our board.”

Sarah M

Homeowner, Westerville

Similar Installations

How site type shapes the right charging mix. Project details shown are sample content.

Featured case study

Workplace Charging

Harbourside Business Park

Workplace and visitor charging for a 1,200-space business park, delivered in two phases.

Location

Bristol, UK

Charging type

24 × AC 22 kW · 4 × DC 60 kW

Scope

Design, grid upgrade, install, support